 |
|
|
| |
 |
| |
BACK TO ARCHIVES
General warehouse in New Orleans, Louisiana on March 21, 1996.
THIS MASSIVE warehouse fire burnt for six days before being
brought under control by the New Orleans Fire Department. The damage,
which was caused by an arson fire and a subsequent electrical fire,
could possibly have been avoided. Complications involving the
sprinklers were to blame, according to the NFPA.
- The 380 m by 278 m large warehouse and distribution facility stored closeouts and
discontinued items in two rack areas. The building structure
consisted of unprotected steel I-beam columns and girders, and roof
support was provided by unprotected metal bar joists. The roof was
constructed of a single-ply membrane with rigid insulation over a
corrugated metal deck. Part of the building was an office area and
segregated storage area that occupied 19,021 m². The roof over
the main warehouse was on two levels. The lower level ranged from
11m to 12m. The upper level, which covered the higher of the two
rack areas, had a maximum height of 22m. The main warehouse floor,
which measured 86,400 m², did not have any fire separation
barriers.
-
- On the south side commodities were delivered by truck, on the north side, they
shipped out. In the east sections of the building there was a low
portable rack storage area. These racks were not equipped with any
in-rack sprinkler systems. The ceiling was 22m high in this area. In
the middle of the building were high-bay rack storage areas. The
racks in these areas were 19m high, 31 m long and 1.2m deep. There
was a mixture of commodities stored on these racks, including:
wicker baskets and furniture; rugs; polyfil pillows; cardboard
boxes; duvets; towels; stacked plastic chairs and plastic bags. In
addition to the racks, the main warehouse area housed a variety of
conveyor systems and a mechanized retrieval system.
-
- The building was equipped with 30 overhead sprinkler systems and 17 in-rack
sprinkler systems. The facility was supplied by a 10 " looped
water main connected to a 20" municipal water main. A 1,135,600
litre water tank provided an additional water supply. Two 9,462
litre/min fire pumps, one electric and one diesel, were connected to
the fire protection system. The electric pump was connected to the
water mains and the diesel pump was connected to the water tank.
-
- The sprinkler
system over the area of the first fire was designed to supply a
density of 18 litre/ min/ ml. However, there were no in-rack
sprinklers in this area. The ceiling was located about 22m above the
floor and 16m above the highest level of racks.
-
- A fire alarm
system monitored the sprinkler systems, valves and fire pumps. Alarm
and trouble signals were transmitted to an on-site security office
that was continually monitored. Alarm signals were transmitted to an
off-premises supervising station that was responsible for notifying
the fire department. At the time of the first fire, there were 15
employees in the building.
- The first fire,
reported at 5.32am, quickly involved the combustible materials being
stored in the 6.4m high portable racks. When the fire was
discovered, it was reported to have fully involved the three-tier
rack, and was extending to the ceiling. The rapid fire spread can be
attributed to the combustible nature of the products being stored
and their storage configuration. Employees tried unsuccessfully to
fight it using portable fire extinguishers and occupant-use fire
hoses. The overhead sprinkler system, that was located approximately
15m above the top level of the racks, activated at 5.32am, but did
not extinguish or control the fire. The fire was extinguished by the
fire department using an interior attack.
- The New Orleans Fire Department responded at 5.37am with an initial attendance of six appliances. The first appliance arrived at 5.40am and reported
heavy smoke showing. Eight additional units were dispatched at
5.42am. The fire was reported to be coming through the roof at
5.43am. Firefighters began an interior operation to contain the
fire. It was declared under control at 8.44am, and extinguished at
11. 54am.
- Once fire
control had been achieved, all the sprinkler systems in the facility
were manually shut down by closing the individual valves on the
risers. According to the New Orleans Fire Department, this was
because numerous sprinkler heads had opened throughout the
warehouse, causing extensive water damage. At 2.20pm, electrical
power was restored to the conveying system within the racks in the
south-central portion of the building. Damaged wiring in this area
arced and ignited combustible materials. As soon as the second fire
was discovered, facility personnel began opening the recently shut
valves on the ceiling and in-rack sprinkler systems. The
catastrophic damage that followed is attributed to the fact that the
sprinkler systems were shut down throughout the entire facility.
Consequently, the sprinkler system was overwhelmed, and the fire
department had to mount a defensive operation.
- This second
fire was declared under control on Wednesday, 27 March 1996 at
9.08pm, six days after the first fire.
-
- The warehouse
and distribution portion of the building, and its contents, were
totally destroyed by the second fire. There was minimal fire and
water damage to the area located on the other side of the fire
separation wall. There was some structural damage to the walls due
to the stresses placed on this portion of the building by the
collapsing roof on the east side of the fire separation wall. On
this side, structural collapse was widespread.
-
- The devastation
caused by the fires was the result of a number of factors,
including:
- excessive
clearance between the ceiling sprinklers and the top of the storage
racks in the area of fire origin for the first fire, lack of in-rack
sprinkler systems ,shutting off all the sprinkler systems in the
building following the first fire restoration of electrical service
without evaluating the damage to the electrical system. This action
was determined to have caused the second fire.
-
- The results of
the FRAME calculation for this case are:
- the area factor g = 8.61
-
the initial risk Ro = 18.87
-
- R = 3.17 , R = 0.94 , R = 1.50 : the property is NOT adequately protected, but the risk for the occupants is acceptable
-
- With this case
study three features of the FRAME method and program can be
illustrated:
- First, the results of the calculation (and the fire itself) show that the
building is not adequately protected, although it is equipped with
sprinklers. FRAME has a built-in balance between risk factors and
protection, which makes that very large compartments with high fire
loads are not considered as acceptable, even with sprinkler
protection.
- Second, the user of the program will not be allowed to introduce the 22 m value
for the ceiling height, as the program accepts only a 15 m maximum.
There are two technical reasons for this limitation : one is that
sprinkler activation will be delayed and sprinkler protection can
become ineffective when there is too much clearance between the
ceiling and the fire seat, as this case illustrates dramatically.
The second reason is that in such high spaces like in atria,
stratification of the smoke layer can occur, making smoke detection,
smoke venting and sprinklers ineffective. By refusing values above
15 m for the ceiling height, the program makes the user aware of the
fact that he is confronted with a special situation where particular
care is required in the design of the fire protection.
-
- The third interesting feature is that the value of Ro gives the designer an
early warning that the risk is too large to be properly protected .
Very large risks shall be provided with redundant protection
systems, which means in practice that the building has to be divided
in compartments ans sprinklered as well.
-
- For this particular case, the report as publicised in Fire Prevention (UK)
issue 300 of June 1997, expressed concerns about the Sprinkler
system performance, as it was not designed according the
requirements of the NFPA codes.
-
- The sprinkler
systems never had a chance to control the second fire because the
main control valves were shut off after the first fire was
extinguished. A sprinkler system's ability to control a fire is
greatly reduced if it cannot operate during the initial stages of
fire development. By the time the second fire was discovered and
efforts were made to open the valves, the fire had grown to a size
where the sprinkler discharge would not have been effective.
- While properly
designed, installed and maintained sprinkler systems have an
excellent record of controlling fires, it can be necessary to employ
a more comprehensive fire protection plan, which accounts for
uncertainties, when extremely large values are at stake.
This is exactly the intention of the built-in balance of risk factors in
the FRAME method.
-
- System impairment
-
During overhaul
operations, all of the ceiling and in-rack sprinkler systems
throughout the building were shut down, despite the fact that fire
damage was limited to a relatively small area in the north-eastern
portion of the building. According to the fire department, it was
necessary to shut off each riser because a number of sprinkler heads
had opened throughout the facility following the first fire.
-
As the electricity
was restored, the second fire broke out in an area remote from the
first and there was no water in the sprinkler systems to control it.
The fact that each sprinkler system was shut off individually
contributed significantly to the resulting destruction of the
building.
-
- Utility
Restoration
-
The restoration of
electricity was done before the electrical system could be fully
evaluated for damage, and before the sprinkler system was made
operable. Failure to isolate or repair the damaged section prior to
restoring power was another key factor in contributing to the
ignition of the second fire. It is imperative that services are
restored in a planned and coordinated manner, and only after a
complete survey of the damage has been taken. There are several
hazards associated with an uncoordinated restoration of utilities.
The potential risk to rescue personnel and other workers operating
in the area during overhaul and restoration is significant. Utility
systems that have been damaged during a fire should be inspected and
repaired before being restored. It is also imperative that everyone
involved with the overhaul and restoration operations be aware of
what actions are being taken by the different agencies and services
involved.
BACK TO ARCHIVES

|